#Softedemy,#PrimaveraP6,#userpreferences

In this video, you will be Explained Resource Assignments in user preferences | settings in Primavera P6 | Advanced Tutorial |

Adding or removing multiple resource assignments on activities options
You can choose to preserve or recalculate units, duration, and units/time. There are two options:

Preserve the Units, Duration, and Units/Time for existing assignments: Select this option for units, durations, and units/time to remain constant when additional resources are assigned to any activity. Regardless of the duration type of activity, the following equation is always true: Remaining Units = Remaining Duration x Remaining Units/Time
Recalculate the Units, Duration, and Units/Time for existing assignments based on the activity Duration Type: This option calculates a resource assignment’s remaining values based on the activity’s duration type, specified in an activity’s General tab.

The simplest way to think of these two options under Calculations User Preference is to say that the first option to Preserve the Units, Duration and Units/Time overrides the Duration Type and assigns every resource with default options.

The second ‘Recalculate’ option tells Primavera P6 to honor the activity’s duration type.

Admittedly this is a slight oversimplification of what’s going on here, but for the purposes of anticipating the effect of this setting on your resource assignments, this article achieves its intended purpose.

Related Video Link

How to Manage User Preferences | Financial Periods | Primavera P6 | Advanced Tutorial
https://youtu.be/m_uDY81K3AI

How to Assign or to Remove Multiple Resources From Multiple or all Activities in Primavera P6 | Tips
https://youtu.be/4xJ128d_riU

Primavera P6 Difference Between Activity Calendar and Resource Calendar | Change Calendar | Tips
https://youtu.be/O4-yRVBuTTM

How to Perform Resource Leveling to activities | Primavera P6 | 19.12 | Advanced Tutorial
https://youtu.be/5YtolP-LVl8

How to Update Resource Schedule Progress | S Curve | Earned Value Curves | Advanced Tutorial
https://youtu.be/fEr60oUdty8

How to Assign Resource Allocations | Primavera P6 | 19.12 | Advanced Tutorial
https://youtu.be/HjmFvkYKBpM

How to track Resource Usage Profile and Spreadsheet | Primavera P6 |19.12 | Advanced Tutorial
https://youtu.be/NFoJ51Su6g8

How to Assign Resources to Activities | Primavera P6 | 19.12 | Advanced Tutorial
https://youtu.be/ZQEwN5PFJ5o

How to Create and Assign Resource Roles | Primavera P6 | 19.12 | Advanced Tutorial
https://youtu.be/WBWKawJhybM

How to Create and Assign Resource Codes | Primavera P6 | 19.12 | Advanced Tutorial
https://youtu.be/17RT-CoHsW0

How to Create Resource Dictionary | Primavera P6 | 19.12 | Advanced Tutorial
https://youtu.be/tlh4nEEXX58

Contact Details

Email for Contact: [email protected]
Facebook Group Link: https://tinyurl.com/yzn34hct
LinkedIn Page: https://tinyurl.com/ke44khv8